The last remaining 11 tonne blade on a 2.5 megawatt wind turbine at Alexandra Dock in Liverpool is lifted into place by cranes. The month-long operation was undertaken by the docks' owners, Peel Holdings, and was a £15m investment which will generate power for the docks and around 5500 nearby homes. The 80m towers and 45m blades weigh 350 tonnes and were assembled by a team from Germany after arriving in sections from the manufacturers in Rostock..